WorksBeing processedOpen Tendering Method (OTM)NCTDhaka

Package: TKBRW-05

Bangladesh Water Development Board (BWDB)Ministry of Water Resources·Tender ID 1340058Balu River T-1/854, Dated: 27/10/2026

Notice description

As published on e-GP, cleaned of markup

Re-excavation of Talna khal and both bank protection work from km. 0.000 to km. 0.500 = 500.00 m. under Dhaka WD Division, BWDB, Dhaka.

Package details

Every field e-GP publishes for this notice

Tender ID
1340058
Reference
Balu River T-1/854, Dated: 27/10/2026
Nature
Works
Method
Open Tendering Method (OTM)
Procurement type
NCT
Evaluation type
Lot wise
Budget type
Development
Source of funds
Government
Ministry
Ministry of Water Resources
Division
—
Procuring entity
Dhaka WD Division, BWDB
Office
Dhaka WD Division, BWDB
Location
Talna, Khilkhet, Dhaka
Category
Building demolition and wrecking work and earthmoving work; Site preparation work; Engineering works and construction works +2 more

Key dates

All dates in Bangladesh time (Asia/Dhaka)

Published
28 Oct 2026, 01:15 pm
Document sales close
18 Nov 2026, 06:00 pm
Closes
19 Nov 2026, 02:30 pm
Opening
19 Nov 2026, 02:30 pm
Security valid to
19 Nov 2026
Tender valid to
19 Mar 2027

Money

Document price and tender security as published

Document price

৳ 5,000

Payable to the procuring entity before submission.

Tender security

৳60.00 Lakh

Security must stay valid until 19 Nov 2026.

Lots & packages (1)

Each lot is bid separately

LotDescriptionQuantity

Eligibility of tenderer

As published — the notice governs

a) Tenderer must be registered in the e-GP portal through BPPA along with valid and updated Trade License, VAT Registration,TIN certificate and National ID card. b) Tenderer must be submitted all the documents freshly (without corrupted). If evaluation committee could be unable to open thefile (corrupted), that/those file(s) will be rejected. c) VAT & IT will be deducted as per the prevailing government rate. No extra claim will be entertained in this regard. d) Tender evaluation will be done following Standard Tender Documents. e) A detailed list of work in hand/on-going works duly signed by the tenderer must be submitted. f) If any kind of obstacles/structures is needed to dismantle to execute the work as per design and specification the tenderer will doit at his/her own cost. No extra claim will beentertained in this regard. g) Quantity and quality of work will be checked by BWDB's Task Force or any other competent authority. h) Payment will be made upon availability of budget/fund. No claim will be allowed. i) Continuation of work could not be hampered by the bidder showing the cause of insufficient Budget Provision & Fund Allocation. j) The work of the package may be totally dropped, decreased or increased as per field condition/design/administrativeapproval/budget allocation. No claim will be entertained in thisregard. k) average annual construction turnover i.e. total certified payments received for contracts in progress or completed under public sector for a period as stated under ITT Sub Clause 14.1(b), substantiated by the payment certificates issued by the Procuring Entity; In case of JV, the business share of the partner shall be taken into consideration to determine the Tenderer’s compliance with the minimum qualifying criteria;

Procuring entity contact

For clarification requests before the deadline

Contact officer
M.L. ShaikatExecutive Engineer
Phone
02-47113852
Address
Wapda bhaban (3rd Floor), Motijheel C/A

Source: eprocure.gov.bd, the official e-GP portal operated by CPTU. This page mirrors the published notice; the e-GP record is authoritative. Always re-check the notice before you submit a bid.

For contractors

Every e-GP notice, scored against what you can actually build

Shohoz Tender reads the e-GP portal every 30 minutes, scores each notice against your company profile, and tells you what to bid on before the deadline sneaks up.

Bid-fit scoring

A 0–100 score from your categories, districts, value band and past work — with the reasoning shown.

Deadline radar

Email and SMS alerts at set intervals, plus corrigenda and cancellations the day they land.

Price intelligence

What this entity awarded before, to whom, and at what discount against the official estimate.